The work to be done, as indicated on a permit issued under this Article shall be commenced and completed within the time limits specified on such permit. If at any time the Public Works Director finds that the delay in the prosecution of completion of the work is due to lack of diligence on the part of the permittee, he may cancel the permit and restore the right of way to its former condition, pursuant to the procedure in Section 32-37.

No changes may be made in the location, dimension or nature of the work to be done nor in the duration, as granted by the permit, including assignment of such permits, except upon a written authorization of the Public Works Director. (Ord. 3472 § 1, 2012; Ord. 3424 § 1, 2009)